Cập nhật tiến độ thi công dự án Khu nhà ở phức hợp cao tầng Thuận An 1&2 ngày 21/11/2024
Tháp A1
- Đổ bê tông zone 2 hầm B3. Đạt khối lượng: 65%
- Chuẩn bị đổ bê tông lót zone 3, 4, 5 hầm B3
- Đang đào đất xuống hầm B3. Đạt khối lượng: 80%
Tháp A2, A3
- Hoàn tất thi công tường vây tháp A2, A3
- Thi công cọc đại trà tháp A2, A3. Đạt khối lượng: 17/406 cọc
RELATED NEWS
On July 28, 2026, Phat Dat Real Estate Development Corporation (HOSE: PDR) announced a share transaction by an internal person, Mr. Nguyen Van Dat, Chairman of the Board of Directors.
(Dan Tri Newspaper) - Transportation infrastructure is no longer just a supporting factor but is becoming a driving force that is changing the way the real estate market develops and values.
Following a payment of more than VND 1,031 billion on July 3, 2026, Phat Dat Real Estate Development Corporation (PDR: HOSE) has increased its total payments related to the development of the Lotte Eco Smart City Thu Thiem to more than VND 2,444 billion.
Total registered FDI capital in Vietnam in the first six months of 2026 reached US$34.65 billion, a 61% increase compared to the same period last year, while disbursed capital reached US$13.03 billion - the highest level for the first half of the year in the past five years.
8 infrastructure, logistics, and public space projects, with a total investment of nearly 250,000 billion VND, were launched on the morning of July 1st, coinciding with the 50th anniversary of Saigon - Gia Dinh being named after President tỷ lệ tỷ số bóng đá.
tỷ lệ tỷ số bóng đá City has decentralized 26 land-related tasks to the commune level, with many procedures such as land allocation, reclamation, and land use conversion being decided by the chairperson of the commune/ward People's Committee according to their authority.
On June 29, 2026, Phat Dat Real Estate Development Corporation (PDR: HOSE) made the first payment of over VND513 billion under the Equity Interest Transfer Agreement for Lotte Properties HCMC Co., Ltd., further advancing its investment cooperation with Lotte Group on the Lotte Eco Smart City Thu Thiem project.
The signing ceremony for the Investment Cooperation Agreement for Lotte Eco Smart City Project between Lotte Group and Phat Dat Real Estate Development Corporation (HOSE: PDR) on June 26, 2026 received coverage from various media outlets. Smart City Thu Thiem giữa Tập đoàn Lotte và Công ty Cổ phần Phát triển Bất động sản tỷ lệ bóng đá đêm nay (HOSE: PDR) ngày 26/6